TM 5-3800-205-10-1
EXTERNAL AIR TRANSPORT BY CH-47 HELICOPTER - CONTINUED
0017 00
MACHINE DISASSEMBLY AND SECTIONALIZATION - CONTINUED
NOTE.
The following step requires three personnel.
36.
Raise bowl lift cylinders and secure:
a.
Simultaneously lift both cylinders and secure using one ratchet strap for each cylinder as shown in the illustra-
tion.
b.
Secure hydraulic hoses with two straps.
STRAPS
STRAP
RATCHET
STRAP
LIFT
CYLINDER
LIFT
CYLINDER
HYDRAULIC
HOSES
37.
Retighten rear stability skid mounting bolts to 375 lb-ft (508 Nm).
38.
Stow the following tools, required for machine assembly after transport, in BII toolbox on rear deck of scraper:
a.
bar, breaker, 1/2 in. drive;
b.
extension, socket, 1/2 in. drive, 5 in. long;
c.
hammer;
d.
handle, 3/4 in. drive;
e.
head, breaker bar, 3/4 in. drive;
f.
punch, drift, brass, 3/4 in.;
g.
socket, 3/4 in. drive, 1-1/8 in.;
h.
socket, 1/2 in. drive, 9/16 in.;
i.
socket, 1/2 in. drive, 15/16 in.;
j.
socket, 1/2 in. drive, 3/4 in.;
k.
wrench, adjustable, 12 in.;
l.
wrench, combination, 7/16 in. (2);
m.
wrench, combination, 1/2 in.; and
n.
wrench, combination, 9/16 in.
0017 00-32