TM 5-3805-260-10
(11) Attach the lower end of the retractor links
(access from steps on side of bowl)
(12) Fold up steps on both sides of the bowl.
c.
Removing Load Transfer Equipment. Nine procedures are necessary to remove load transfer equipment.
(1)
Start the engine, raise the bowl about one
foot and open the bowl floor about six
inches. Place a block under the cutting
edge to keep the load transfer wheels off
the ground. Lower the load transfer axle.
Stop the engine.
1-59