oFigure 15. Installation of Bushings onto Apron Assembly.
Figure 16. Ripper Blade and Apron Assembly.

Maintenance Manual For The Hydraulic Blade Folder-Track Tensioner For Armored Combat Earthmover, M9
Page Navigation
  126    127    128    129    130  131  132    133    134    135    136  
img
TM 5-2350-377-13&P
0036
ASSEMBLY - Continued
2.
Install two bushings (Figure 16, Item 2), four retaining rings (Figure 16, Item 3), and two lubrication fittings
(Figure 16, Item 1) on each side of apron (Figure 16, Item 7). Coat inside of bearings (Figure 16, Item 2) with
grease and apply grease to lubrication fittings (Figure 16, Item 1).
NOTE
Step (3) should be performed only if plugs are missing.
3.
Coat threads of two plugs (Figure 16, Item 14) with sealing compound, and install two plugs
(Figure 16, Item 14) on apron (Figure 16, Item 7).
NOTE
If ripper blade is to be folded, perform Step (4).
If ripper blade is unfolded, perform Step (5).
4.
Install latch (Figure 16, Item 8) on each side of apron (Figure 16, Item 7) with pin assembly
(Figure 16, Item 13) and linchpin (Figure 16, Item 9).
5.
Install latch (Figure 16, Item 8) (facing in) on each side of apron (Figure 16, Item 7) with pin assembly
(Figure 16, Item 13) and linchpin (Figure 16, Item 9).
NOTE
For ripper blade application, install stop with words "ripper blade" facing out.
For cutting edge application, install stop with words "standard blade" facing out.
6.
Install stop (Figure 16, Item 11) on each side of apron (Figure 16, Item 7) with screw (Figure 16, Item 12) and
locknut (Figure 16, Item 10).
7.
Install three rings (Figure 16, Item 6) on rear of apron (Figure 16, Item 7) with three straps
(Figure 16, Item 5) and six new machine bolts (Figure 16, Item 4).