TM 5-3805-248-23-2
STEERING FLOW METER TEE TEST PROCEDURES - CONTINUED
0306 00
NOTE
Hydraulic system tests are performed when required by troubleshooting to confirm a problem or iden-
tify a faulty component within the system. These tests can also be performed after repair operations to
ensure faults have been corrected and performance is within specifications.
Hydraulic system tests consist of operating checks and analysis of test results to determine if corrective
action is needed.
Perform PMCS for hydraulic system as outlined in WP 0019 00 and WP 0020 00 before performing
tests.
PREPARATION FOR TEST
1.
Loosen cap on hydraulic tank and release any pres-
HYDRAULIC
sure. Tighten cap.
TANK CAP
2.
Start engine and move ejector control lever fully for-
HYDRAULIC
ward. Stop engine.
IMPLEMENT PUMP
PLUG, PREFORMED PACKING
WARNING
Do not install the flow meter adapter into
the supply line of the implement pump
with the engine running. Failure to do so
may cause injury. If you are injured, seek
medial attention immediately.
NOTE
Install adapter quickly to minimize loss of
oil.
3.
Remove plug and preformed packing from the supply
side of implement pump. Install adapter. Install return
line and connect to flow meter.
0306 00-2