TM 5-3805-248-23-2
EJECTOR GUIDE ROLLERS MAINTENANCE - CONTINUED
0331 00
CLEANING AND INSPECTION - CONTINUED
3.
Inspect all parts for damage and replace as necessary.
ASSEMBLY
1.
Use a driver and hammer to install cup (17) up into roller (1) and seat against counterbore in roller.
2.
Use a driver and hammer to install cup (16) down into roller (1) and seat against counterbore in roller.
3.
Lubricate and install cone (14) up into roller (1). Apply grease evenly to cone bearing surface.
4.
Use grease to lubricate lip of seal (13).
5.
Use a driver and hammer to install new seal (13) up into roller (1) with lip toward inside of roller. Seat firmly against
bottom of counterbore.
6.
Install shaft (5) up into roller (1).
7.
Lubricate shaft (5) and roller (1), and apply grease heavily to inside area.
8.
Lubricate and install cone (15) down into roller (1). Apply grease evenly to cone bearing surface.
9.
Install washer (10), lock (9) and nut (8). Hand tighten nut until roller will not rotate on shaft. Back off nut 1/16 turn.
10.
Install new gasket (12), cap (11), four washers (7) and bolts (6).
INSTALLATION
1.
Install ejector guide roller (1) on ejector frame.
2.
Rotate shaft (5) until clearance between ejector and bowl is 0.12 in. minimum to 0.75 in. maximum.
3.
Install washer (4), bolt (3) and nut (2), mounting ejector guide roller (1) to ejector frame.
4.
Operate machine and verify correct ejector operation (TM 5-3805-248-10).
1
2
5
4
3
394-1459A
END OF WORK PACKAGE
0331 00-3/-4 Blank