TM 5-3805-260-10
(3)
Removal of right and left elevator chain rollers. Contact Organizational maintenance.
(4)
Removal of every other elevator flight (8 total). Contact Organizational maintenance.
(5)
Removal of load transfer equipment. See Chapter 3, Preparation For Helicopter Transport, Removing Load
Transfer Equipment (page 3-13).
(6)
Sectionalization procedures (install steer axle and sectionalize). See Preparation For Helicopter Transport,
Sectionalization Procedures (page 3-14).
(7)
Weight distribution procedures. Additional components must be removed and mounted in their storage position
for proper weight distribution. The fuel tank must be filled to 25 percent capacity before proceeding with
sectionalization procedures. See Preparation For Helicopter Transport, Weight Distribution (page 3-24).
(8)
Install helicopter lift slings. See Figures 1 and 2 (pages 3-3 and 3-4), and appropriate Army approved bulletins
for helicopter slinging procedures.
(9)
Prepare a separate overpack box for the ROPS, elevator rock guard, elevator chain rollers, the elevator flights,
and hardware.
b.
Preparation For Operation After Helicopter Transport. Six procedures are required to prepare the Tractor-Scraper
after helicopter transport.
(1)
Preparation for reconnection. See Assembly After Helicopter Transport, Preparation For Reconnection (page 3-
29).
(2)
Reconnect tractor and bowl sections. See Reconnection (page 3-33).
(3)
Install 8 elevator flights. Contact Organizational maintenance.
(4)
Install rock guard. Contact Organizational maintenance.
(5)
Install elevator chain rollers. Contact Organizational maintenance.
(6)
Install rollover protective structure. Contact Organizational maintenance.
3-7