BOWL LIFT CYLINDERS REPLACEMENT - CONTINUED
0242 00
INSTALLATION - CONTINUED
6.
Install new preformed packing (8) and tube assembly (7).
7.
Install four washers (6) and capscrews (5) on tube assembly (7).
8.
Install new preformed packing (10), hose assembly (13) and two flange halves (9) on bowl lifting cylinder (4).
9.
Install four washers (12) and capscrews (11).
7
8 (HIDDEN)
5,6
9,10
(HIDDEN)
11,12
13
4
394-562
10.
With assistance, position bowl lifting cylinder (4) and install pin (2).
11.
Install pin (3) and bolt (1) in bowl lifting cylinder (4).
4
3
2
1
394-555
12.
Fill hydraulic tank to correct level (TM 5-3805-248-10).
13.
Operate engine and verify correct operation of bowl lifting cylinders (TM 5-3805-248-10).
14.
Completely raise and lower bowl 5 times to purge air from system.
15.
Shut down engine (TM 5-3805-248-10).
16.
Check oil level in hydraulic tank and add if necessary (TM 5-3805-248-10).
17.
Inspect all hose and tube assemblies for leaks.
END OF WORK PACKAGE