TM 5-3805-248-23-2
DRAFT FRAME ASSEMBLY SHOES MAINTENANCE - CONTINUED
0314 00
REMOVAL
NOTE
Right and left draft frame assembly shoes are replaced and adjusted the same way. Right draft frame assem-
bly shoe is shown.
1.
Lower bowl until assistant indicates that draft assembly shoe is accessible, forcing bowl against ground to raise rear of
scraper.
WARNING
Do not work under scraper bowl assembly when wheels are raised off ground. Support bowl assembly with
two jack stands placed under frame. Ensure that tractor wheels are chocked to prevent machine from rolling
or shifting. Failure to follow this warning may cause injury.
2.
Position jack stands under bowl assembly frame at rear of bowl.
3.
Raise bowl assembly until it settles on jack stands, then move control to HOLD position.
4.
Remove three bolts, draft frame assembly shoe and
shim pack from draft frame. Tie shim pack together
BOLT
and tag to aid in installation.
SHOE
SHIM
DRAFT
FRAME
394-1016
0314 00-2