Figure 5. Control Box.
ELECTRICAL SYSTEM - Continued

Maintenance Manual For The Hydraulic Blade Folder-Track Tensioner For Armored Combat Earthmover, M9
Page Navigation
  37    38    39    40    41  42  43    44    45    46    47  
img
. .
TM 5-2350-377-13&P
0012
ELECTRICAL SYSTEM - Continued
STEP
8.
Check control box for continuity.
a.
Push left side track tensioning switch (Figure 6, Item 1) up.
b.
Check continuity between connector pins on connectors J1 (Figure 6, Item 3) and J2 (Figure 6, Item 2).
c.
Refer to Table 3 for lead locations.
d.
Release left side track tensioning switch (Figure 6, Item 1).
2
1
3
T00406HBF
Figure 6.
Control Box Connectors J-1 and J-2.
Table 3. Control Box Left Side Tension Switch.
POSITIVE LEAD
NEGATIVE LEAD
J-1 (4)
J-2 (3)
J-1 (4)
J-2 (3)
C
D
D
D
CONDITION/INDICATION
Is continuity present at left side track tensioning switch?
DECISION
YES - If continuity is indicated, go to Step (9).
NO - If an open circuit is indicated, replace control box wiring harness (WP 0027). Verify problem is solved.
0012-7